Overview
The Checks step of the BESS Designer runs the validators on a placed layout, and the Reports step opens the result windows. The compliance check tests every unit against the rule set from the Verifications step and cites the rule behind each finding.
Supported rule sets are NFPA 855 (2020, 2023 and 2026 editions), IFC (2018, 2021 and 2024) and manufacturer clearances only.
Prerequisites
Units placed, exposures tagged, and a rule set and any AHJ overrides entered in the Verifications step.
Step-by-Step Guide
1. Run the compliance check
In the Checks step, click Run compliance check. The BESS Code Compliance window opens and checks the layout right away. The header of the Checks step shows the number of warnings found.
2. Read the findings
The window shows the rule set in use and a summary of pass, warning or fail. Findings are grouped by severity. Each finding has a message and its source: a code reference such as NFPA 855-2023 §9.5.2.6.1, AHJ override when you overrode that value, or Manufacturer clearance when the enclosure’s own clearance governs.
3. Check the rules in effect
Expand Rules in effect to see every value the check applied (exposure setback, reduced exposure setback, group separation, energy caps, remote-location threshold, fire lane width) and where it came from. Use it to confirm which setback was applied before you send a layout for review.
4. Understand the reduced setback
The reduced exposure setback applies to a unit whose enclosure has UL 9540A test data in its catalog entry (Has UL 9540A test data). Units without it get the full exposure setback.
5. Fix and re-run
Move units, change the layout or, where your AHJ agrees, enter an override. Then click Re-run in the report window.
6. Open the reports
The Reports step has three buttons. Compliance opens the same compliance window and shows the warning count in its caption. Augmentation opens the augmentation plan. Pad grading runs pad grading and opens its report, the same action as the Grading step.
Tips & Recommendations
- Reserve pads are included in compliance checks even though they are excluded from the energy totals.
- The flood check against Minimum pad elevation reports with the source “project setting”, not a code reference. Pads outside the terrain are skipped with a note.
- Noise results at tagged lot lines above 55 dBA appear as warnings. That threshold is planning guidance, not a code limit.
- Set Validation gate to Block on errors if compliance errors must stop an auto-placement.
- The check advises, it does not certify. Confirm every rule with your Authority Having Jurisdiction.