Placing BESS Units and PCS Skids (Placement Step)

Overview

The Placement step of the BESS Designer fills a BESS area with battery units, either automatically or one unit at a time with live clearance checking. It also pairs PCS skids with DC-block containers and holds the tools you need after placement: fire lanes, reserve pads and removing all units.


Prerequisites

A BESS area with its exposures tagged, a rule set chosen in Verifications, and a storage unit selected in Settings. For AC-coupled units, the plant transformers should already be placed.

Step-by-Step Guide

1. Choose the sizing mode

Select Fit to capacity and type the energy you need in Target (MWh), or select Maximize to fill the area as far as the clearances allow. In fit mode the line under the target shows how many units reach it and their total MWh and MW. If the target text is not a valid number, the field turns red and auto-placement does not run.

Fit to capacity sizes against the target and the area you fill. It does not read the point of connection limit. Each run fills one area to the full target, so if you split storage across several areas, set the target per run.

2. Decide on reserve pads

In fit mode, tick Plan augmentation reserve pads to also place spare pads for future capacity. It is off by default, so a target on its own places exactly the units needed. The option is hidden in maximize mode.

3. Run auto-placement

Click Auto-place units. If the drawing has several BESS areas, select the one to fill at the command line. A preview window shows the per-unit usable energy (nameplate multiplied by DoD), the number of energized units, whether the target is met, the reserve pads, the fire lanes and a validation summary. Click Place to commit or Cancel to stop. With the gate set to Block on errors, nothing is placed while code errors remain.

If most AC-coupled units would connect to one transformer, the Distribute BESS Units window offers to spread them evenly. It shows each transformer’s headroom before and after and flags any that would exceed its rating. Click Distribute or Keep Nearest.

4. Place units by hand

Click Manual, pick an enclosure in Select BESS Enclosure, then click in the drawing to place units. The ghost turns red where the spacing would be violated, so a click in a clear spot commits one unit.

5. Pair PCS skids for DC blocks

A DC-block container needs a separate PCS skid. An AC block has the PCS built in and needs nothing else. Auto-placement tries to place a PCS skid next to each DC-coupled unit. To add one by hand, click PCS skids, pick a DC container, move the skid into position and click. A container takes one skid.

6. Use the tools after placement

  • Regenerate lanes: recomputes the fire lanes from the units now in each area. Use it after hand edits.
  • Reserve pads: pick a unit to switch it between energized and augmentation reserve. Totals update with it.
  • Remove all: removes every placed BESS unit after a confirmation.

Tips & Recommendations

  • Battery containers, PCS skids and transformers are separate objects only where the hardware is separate: a DC block plus its PCS skid are two objects, an AC block is one. There is no BESS-specific transformer object. AC-coupled units connect to the transformers you place in the electrical design.
  • Effective spacing is the larger of the manufacturer’s maintenance clearance and the code separation.
  • Units are drawn true to scale. PV racks under a unit or skid are deleted and listed in the Racks removed window.
  • Placement commits are a single undo.