Layout Using Capacity Iteration

Overview

Capacity Iteration runs the Build Layout placement for a range of spacings (and optionally tilts) without drawing anything, and lists the DC capacity, rack count and module count of each scenario. You pick the scenario you want and PVX.AI builds it. The prediction uses the same inputs as Build Layout: boundary roads and setbacks, exclusions, roads, corridors, slope limits and drawing units.


Prerequisites

PV areas, and racks chosen with Select Rack in Build Layout: Capacity Iteration uses the racks and placement direction set there. If none are set, the window shows No racks selected.

Step-by-Step Guide

1. Open Capacity Iteration

On the Layout panel, open the Tools dropdown and click Capacity Iteration. You can also open it with the Capacity Iteration button at the bottom of the Build Layout window.

2. Choose the PV areas

Under Selection Context, click Select Boundaries to pick PV areas, or All Boundaries to use every PV area in the drawing.

3. Choose the spacing mode

Under Iteration Parameters, set Spacing Mode:

  • Row Spacing: iterates the clear gap between rows, in drawing units. Use it when the gap itself is the constraint, for example a vehicle width.
  • GCR (ratio): iterates the ground coverage ratio, the rack depth divided by the pitch. Use it to compare with a PVsyst model or a specified GCR; the same GCR means the same row geometry whatever the rack size.
  • Shading Angle (°): iterates the sun elevation at which rows stop shading each other, and derives the pitch from it. Use it when your design rule is a no-shading angle.

Enter the Spacing Range as From, To and Step.

4. Add tilt and a target (optional)

Tick Tilt Angle and enter From, To and Step in degrees to compare tilts of fixed racks. Tick Capacity Target and enter the target in kWp.

5. Iterate and pick a scenario

Click Iterate. The Results table lists each scenario with Row Spacing, Tilt (deg), GCR, DC Power (kWp), Racks, Modules and Delta (kWp) against your target. Tick Pin on a row to keep it when you iterate again. Tick 3D to build the scenario on the terrain. Select a row and click Generate Selected Layout.

6. Hitting an exact capacity, for example 50 MW

First decide whether 50 MW is DC or AC.

  • 50 MWp DC: enter 50000 as the Capacity Target. A layout is made of whole racks, so no scenario lands exactly on the target. Run a coarse range first, then a second run with a small step around the best scenario (for example 0.05 m of row spacing or 0.005 of GCR). Build the scenario just above the target and remove the last racks, usually at a ragged area edge, until the BoQ shows the capacity you need.
  • 50 MW AC: AC capacity comes from the inverters, not the racks. Choose a DC/AC ratio, set the DC target to AC times the ratio (50 MW at 1.25 gives 62.5 MWp), and build that. Then, in the electrical design, set the string inverter configuration by DC/AC ratio: or by strings per inverter (Str/inv:); strings per inverter = inverter kW × 1000 × ratio / string W. The number of inverters times their AC rating gives your AC capacity.

Tips & Recommendations

  • The prediction matches Build Layout at a fixed spacing. A build with Dynamic Pitch places a different number of rows, and on a rotated azimuth the count can differ by a few racks.
  • Capacity Iteration works for fixed, east-west and tracker racks, and follows the corridor pattern stored on each PV area.
  • Pin the scenarios you want to keep before you change the range and iterate again.