DC and AC Cabling

Overview

Cabling draws the routes from strings to DC boxes or inverters, from DC boxes to inverters, and from inverters to transformers, and sizes every cable. It is step 5 of the Electrical Design window and runs on the PVX.AI cloud cabling engine. The placement mode decides who controls the routes: in Auto mode cables follow the roads, in Manual mode they follow the trenches you assign.


Prerequisites

Strings drawn and devices placed. If you moved devices by hand, run Adapt Devices first so cabling uses their new positions.

Step-by-Step Guide

1. Auto mode: cabling runs after placement

With Auto placement, cabling starts by itself once every transformer of the PV area is placed. If placement stopped part-way, no cabling runs; the command line names the transformers still to place, and cabling follows when you press Place Devices again and finish them.

2. Manual mode: prepare the trenches

In Manual mode you decide where cables run. Use Electrical sub-tab > Trenches > Generate Trenches from Roads to start from the service roads, or draw your own trench routes as polylines. You can mix both.

3. Manual mode: assign trenches to each transformer

In step 5 of the panel, click Assign DC Trench, pick a transformer, then select the polylines its DC cables may use. Repeat with Assign AC Trench for the inverter-to-transformer cables. The same commands are in the Trenches menu as Assign DC Trench to Transformer and Assign AC Trench to Transformer. Highlight Trenches highlights the trenches in the drawing.

4. Generate or regenerate the cables

Click Electrical sub-tab > Cables > Regenerate Cabling; in Manual mode the same button is in step 5 of the panel. In Manual mode the cables are routed only along your trenches; roads are not used, and with no trench in the drawing the run stops before anything is sent. One run cables one PV area. PVX.AI takes the area from the panel, from a selected PV area boundary, or from the selected strings; otherwise it asks you to pick one PV area. Picking two is refused.

5. Review the result

Cables are color-coded by device group and each one is sized for ampacity and a voltage-drop target; see Voltage Drop in Cabling. Strings with no transformer have their cables painted red. To check lengths and sizes, draw the tables with Information > Cable Information Table or export them with Cables (XLS).

6. Clear cables or trenches

The Cables menu clears cables of the whole design (Clear All DC Cables, Clear All AC Cables) or of one device (Clear Cables of Transformer, Clear DC Cables of Inverter and so on). On a drawing with two or more PV areas, the Clear All buttons, Clear All Trench Assignments, Remove All Trenches and Remove All Devices act on the PV area boundaries you have selected, or show a menu: Pick PV areas or Whole drawing. The confirmation names the areas and what will change. Items that belong to no PV area are kept unless you choose Whole drawing. Each clear is one Ctrl+Z.


Tips & Recommendations

  • Cables follow the rows of a PV area at any azimuth. On a site that mixes fixed-tilt and tracker areas, each area is routed in its own style.
  • To steer a route in Auto mode, switch to Manual, generate trenches from roads, edit or add trench polylines where you want cables to run, assign them and regenerate.
  • On a multi-area site the cable tables are written one per area: DC Cables (PV-1), DC Cables (PV-2), AC Cables (PV-1) and so on. A single-area drawing keeps the plain table names.
  • After cabling, draw construction details with Trench Sections; see Trench Engineering and Cable Generation.