Overview
Cabling turns placed devices into routed cables, and trench engineering turns those routes into trenches that can be built: grouped lanes, DC ducts, burial depth and cross-section details. The trench settings also feed the cable sizing, because derating depends on how the cables are installed.
Prerequisites
Devices placed in step 4 of the Electrical Design window. Manual mode also needs roads or your own trench polylines.
Step-by-Step Guide
1. Set the trench engineering before cabling
In the Electrical Design window, open the trench settings card under Trenching & route planning. It shows a live cross-section preview. Choose the IEC 60364-5-52 installation method and cable separation, or leave them to PVX.AI, and set the trench geometry and DC ducts. Derating for buried runs reads the clearance actually drawn, so the sized cables match the trench that gets built.
2. Auto mode: cables follow the roads
With Auto placement, cabling runs once every transformer is placed and the routes follow the service roads. Re-run it with Electrical sub-tab > Cables > Regenerate Cabling, one PV area per run.
3. Manual mode: cables follow your trenches
Run Trenches > Generate Trenches from Roads, or draw your own trench polylines where you want cables to run. Use Assign DC Trench and Assign AC Trench in step 5 of the panel to pick a transformer and select its polylines, then click Regenerate Cabling. Cables are routed only along the assigned trenches. To change a route, edit or add polylines, assign them and regenerate.
4. How routes become trenches
Cable runs that share a path are grouped into trench lanes, DC strings are packed into ducts, and lane groups that get too large are split into parallel trench banks.
5. Drape and detail
Cables > 3D Drape converts cables and trenches between flat 2D and terrain-draped 3D polylines, which gives true 3D lengths and a burial profile. Then click Electrical sub-tab > Trench Sections to draw cross-section details with polarity colors, hatches, duct labels and a depth ladder, linked to the plan by leader balloons.
Tips & Recommendations
- Trench design uses IEC 60364-5-52 only. There is no NEC installation-method table.
- Trench section details are not removed when you clear cables or trenches. Run Trench Sections again after regenerating.
- Clear All Trench Assignments keeps the trench polylines; Remove All Trenches deletes them. On a multi-area drawing both ask which PV areas to act on.