Overview
A storage site with no solar runs through the same BESS Designer as a combined plant. This guide covers the standalone workflow and how to edit a design that is already placed.
Prerequisites
Terrain imported, since pad grading needs it.
Step-by-Step Guide
1. Start a standalone plant
Skip the PV layout. Open Electrical sub-tab > Electrical Design > BESS Designer and work through BESS Area, Verifications and Settings, then click Auto-place units on the Placement step. Auto-placement works with no PV areas in the drawing.
2. Give the units a parent
Place the transformers (for AC-coupled units) or inverters (for DC-coupled units) with the electrical device tools, so each unit has a device to connect to. Compliance, cabling, grading, augmentation, noise and yield then run as in a combined plant.
3. Move a unit
There is no move button for BESS units. Use AutoCAD MOVE or grips on the unit’s block, and select its name label and, for a reserve pad, its hatch in the same move: nothing moves them for you afterwards. Avoid ROTATE for now, because the footprint clean-up still follows the stored orientation.
Adapt Devices covers inverters, transformers and DC boxes only. It does not handle BESS units or PCS skids yet. PV racks under the new position are removed at the next footprint refresh, for example Devices > Refresh Trafo Footprints or a cabling run. Racks removed at the old position do not come back.
4. Delete units or clear the area
To delete one unit, select its block and press Delete. To clear all units, click Remove all on the Placement step and confirm. To delete a BESS area, select its boundary polyline and press Delete. If cables exist, the Regenerate Cabling? prompt asks whether to regenerate now.
5. Refresh the derived work
After edits, click Regenerate lanes (Placement), Run compliance check, Noise and Vegetation (Checks), Generate cabling (Cabling & yield) and Grade BESS pads (Grading) as needed. Lanes, rings and contours are replaced, not duplicated.
Tips & Recommendations
- Area draws, placement commits, unit deletes, reserve toggles and a whole grading run are each a single undo. A native move is one undo.
- Grading volumes stay consistent after edits because they are measured against the original terrain.