Collision Analysis

Overview

Collision Analysis checks whether a placed layout can be built on its terrain. For every rack in a PV area it measures the ground clearance along the whole row, the pile reveal at every pile and the ground slope under the rack, compares them with your limits, and ranks what is out of range. It then offers fixes in order of cost: lift racks, regrade the rows that still miss as one continuous surface, or adapt the terrain to the piles. The results can be exported as a pile schedule and a report.


Prerequisites

A PV area with racks placed on terrain. The rack specs should have their real pile depth and, for trackers, the torque tube set.

Step-by-Step Guide

1. Open the panel and pick the area

On the Layout panel, click the Collision Analysis button (the arrow below it opens Adapt Terrain to Pile and Generate Cross-Section). Click Select PV area and pick the area boundary. The scan, the limits and every fix act on one area at a time.

2. Review the limits

The Limits pane is filled from the rack specs in the area; Reset to rack defaults restores them. Edit them to match the project requirements:

  • Minimum ground clearance and Maximum ground clearance
  • Minimum pile reveal and Maximum pile reveal
  • Maximum slope along the rack and Maximum slope across the rack

Terrain-following frames are judged against the bands in their own rack spec, not against these boxes.

3. Know the difference between clearance and reveal

These two limits are often mixed up, and mixing them up makes a site impossible to fix.

  • Pile reveal is the length of a pile above the ground: pile head height minus the ground under that pile. It is measured at every pile and decides which pile lengths you order. Below the minimum needs fill or a longer pile; above the maximum needs cut or a shorter pile.
  • Ground clearance is the gap between the structure and the ground anywhere along the row, not only at the piles. Fixed tables are measured under the front (low) and back rails. Trackers are measured under the module’s lowest edge at maximum tilt, on both sides, and under the torque tube.

On a tracker the module edge at full tilt hangs below the pile head, so the clearance is always smaller than the reveal. A requirement of “minimum ground clearance 1.0 m” therefore needs a maximum pile reveal well above 1.0 m. If you type the clearance figure into Maximum pile reveal, no rack can meet both. The panel detects this, states the shortfall with the exact numbers, and offers Raise the maximum reveal to or Lower the floor to a value that works.

4. Set the tolerances

Under Advanced, Warning tolerance for clearance and reveal (m) and Warning tolerance for slope (°) set a measurement allowance: a value past its limit by no more than this is reported as Marginal instead of Violating. Largest shift the analysis may suggest caps the vertical lift it proposes; a rack that needs more is reported as needing grading. Clear the checkbox for no cap.

5. Run and read the results

Click Run analysis. The summary shows how many racks are violating, marginal or skipped. The grid lists each finding with Severity, Finding, Rack, Family, Measured, Limit, Worst point and Suggested fix, worst first. Select a row to zoom to the rack; double-click to jump into the drawing. An overlay marks the violating racks, and Overlay pile labels chooses which piles get a reveal label. Clear overlay removes it.

6. Fix, cheapest first

  • Apply selected shifts: for rows whose suggested fix is a shift, moves the racks up or down as a whole. No ground is moved.
  • Fix collisions: opens a dialog that shows the design numbers per rack spec and a plan of what will happen with an earthwork estimate. Options are Grade the terrain first (smooth the area to the N-S and E-W target slopes before adapting) and Limit earthwork per pile and rack lift. Click Run design: racks are lifted where that is enough. The rows that still miss are regraded as one continuous, buildable surface with the least cut and fill that clears every rack, and the rest of the site is left as it is. The result reports racks lifted, racks graded, cut and fill.
  • Adapt terrain to piles: sends the selected racks to the Adapt To Pile tool, with the rest of the area held as it is.

Run the analysis again after each fix. Where tracker tables meet end to end at different heights, use the Row Adjustment tab, described in Row Adjustment: Level Rows.

7. Export

From Export, save Pile schedule (CSV) or Pile schedule (XLSX) (one row per pile with its reveal and verdict) and Report (HTML) or Report (CSV) with the limits and results, for the structural reviewer.


Tips & Recommendations

  • Results go stale as soon as the drawing changes. The panel tells you and asks you to run the analysis again; exports are refused until you do.
  • Multi-row tracker groups are judged and shifted as one unit.
  • For a tracker, the clearance floor in Fix collisions is applied at the torque tube; the re-scan afterwards measures the real swept module edge.
  • For a quick visual check before running the full analysis, see Spotting Conflicting Racks.