Erosion Analysis and Controls

Overview

Erosion Controls estimates how much soil the site will lose to rain and proposes the structures that keep it on site. It computes soil loss with the RUSLE method, then sizes and places check dams, sediment basins, diversion swales and silt fences, and draws them with quantity tables. The calculation runs in the PVX.AI cloud, using rainfall and soil data for the site’s location unless you enter your own values.

Use it when preparing a stormwater or erosion-control plan, typically after grading, since bare graded ground erodes most.


Prerequisites

Terrain in the drawing, at least one PV Area, and a coordinate system for the project. The analysis runs over the largest PV Area in the drawing.

Step-by-Step Guide

1. Open the dialog

Click Civil Analysis on the PVX.AI ribbon, then go to Civil sub-tab > Analysis > Erosion Controls.

2. Check the coordinate system

If the Coordinate System section shows none, click Pick Coordinate System…. The analysis needs the location to fetch rainfall and soil data.

3. Set the inputs

  • Design Storm Return Period (yr): the storm the structures are sized for (default 2 years). Use the value your permit or local guidance asks for.
  • Check Dam Height (m): the height of each check dam in the channels (default 0.6 m).
  • Basin Min. Contributing Area (ha): a sediment basin is proposed only where at least this much area drains to one point (default 4 ha). Below this, no basin is proposed.
  • Sizing Criterion: SCS Curve Number (runoff volume) sizes basins from the runoff of the design storm, so the result follows the site’s rain and soil. EPA static (3,600 ft³/acre) applies a fixed storage volume per acre drained; choose it when the permitting authority uses that rule.
  • Delineate subcatchments (on by default): splits the site into watersheds so each structure is sized for the area that drains to it.

4. Override the RUSLE factors (optional)

Expand Advanced (RUSLE Overrides) to enter your own Rainfall Erosivity R, Soil Erodibility K (SI), Cover-Management C (operational) and Support Practice P. Leave them blank to use the defaults fetched for the site location from global datasets (GloREDa for rainfall, SoilGrids for soil). Enter values when you have a site soil report or local rainfall data.

5. Run and review

Click Run Erosion Analysis. When the cloud job finishes, PVX.AI draws erosion-risk zones coloured by severity, the proposed basins, check dams, swales, silt fences and culvert points on their own PVXAI_Erosion layers, and quantity tables for the structures.


Tips & Recommendations

  • Run Hydrology Analysis first to see the drainage paths, so the proposed structures make sense on the drawing.
  • Re-run after any regrading: soil loss depends on slope length and steepness, which grading changes.
  • The cover-management factor C describes the ground cover in operation. If you have a revegetation plan, enter the C value for the planned cover.
  • Treat the result as a screening design. Final structures need a local engineer’s review.